Right-of-Way Survey Process

A complete 6-step guide — from record research and field survey through ROW determination, encroachment identification, and map delivery.

Quick Answer

A ROW survey follows 6 steps: record research → control survey → field data collection → ROW line determination → map preparation → delivery. Residential ROW surveys take 2-4 weeks. FDOT corridor projects take 4-8+ weeks.

The most critical step is record research — the surveyor must find every document that defines the ROW: deeds, plats, road dedications, and FDOT maps. This research drives the accuracy and legal defensibility of the final ROW determination.

Process Overview

1

Record Research & Title Review

3-10 days

2

Control Survey & Field Preparation

1-2 days

3

Field Survey & Data Collection

1-5 days (depends on corridor length)

4

ROW Line Determination

3-7 days (office)

5

ROW Map Preparation

1-2 weeks

6

Delivery, Monumentation & Reporting

3-7 days

1

Record Research & Title Review

Typical duration: 3-10 days

Research all recorded documents that define the right-of-way and adjacent property boundaries.

  • Obtain deed for the subject property and all adjoining parcels
  • Research recorded plats, road dedication documents, and county road maps
  • Review FDOT ROW maps and county public works records for public roads
  • Examine title commitment for easements, restrictions, and encumbrances
  • Identify any vacated roads, abandoned easements, or prescriptive use claims
  • Collect all prior surveys of the property and adjoining parcels
  • For FDOT projects: obtain PD&E study results and approved alignment data
2

Control Survey & Field Preparation

Typical duration: 1-2 days

Establish horizontal and vertical control for the survey and prepare for field measurements.

  • Set primary control points using RTK GNSS tied to the Florida State Plane Coordinate System
  • Establish vertical control using NAVD88 datum if elevations are required
  • Recover existing survey monuments along the ROW corridor
  • Set reference points and offset stakes for field survey
  • Coordinate with property owners for access to private property adjoining the ROW
  • For corridor projects: plan traverse along the full length of the ROW
3

Field Survey & Data Collection

Typical duration: 1-5 days (depends on corridor length)

Measure the ROW boundaries, locate improvements, and identify encroachments.

  • Locate existing ROW monuments, boundary markers, and property corners
  • Measure all improvements within and adjacent to the ROW: fences, walls, driveways, utilities, signs
  • Identify and measure all encroachments into the ROW (structures, landscaping, parking)
  • Collect topographic data if required (grades, drainage, pavement edges)
  • Document visible evidence of use: worn paths, tire tracks, maintained areas
  • For FDOT corridor surveys: survey 264 feet in each direction from center points
  • Photograph conditions for documentation and dispute resolution support
4

ROW Line Determination

Typical duration: 3-7 days (office)

Analyze field data and records to determine the legal ROW boundaries.

  • Compare field evidence to recorded documents: do monuments match legal descriptions?
  • Resolve discrepancies between deeds, plats, and physical occupation
  • Compute ROW boundary lines from the controlling legal description
  • For platted roads: retrace ROW from the recorded plat dimensions
  • For dedicated roads: compute ROW from the dedication document and original survey
  • For prescriptive ROWs: document evidence of public use, maintenance, and duration
  • Verify the ROW width matches county records and FDOT designations
5

ROW Map Preparation

Typical duration: 1-2 weeks

Draft the ROW map showing boundaries, encroachments, and relationships to adjacent parcels.

  • Draw ROW boundaries with bearings, distances, and curve data
  • Show relationship of ROW to adjacent property lines (setbacks, overlaps)
  • Label all encroachments with type, dimensions, and distance into the ROW
  • Show all easements within and adjacent to the ROW corridor
  • Include recorded references: plat book/page, deed book/page, instrument numbers
  • Add surveyor certification, signature, and seal
  • For FDOT projects: prepare ROW map per FDOT format and standards
6

Delivery, Monumentation & Reporting

Typical duration: 3-7 days

Set monuments, deliver final documents, and provide an encroachment report if applicable.

  • Set or replace ROW monuments at key points if authorized and required
  • Deliver signed and sealed ROW map (PDF and DWG/DXF)
  • Provide encroachment report listing every intrusion into the ROW with dimensions
  • If FDOT project: deliver per FDOT electronic file standards
  • Archive field notes, calculation sheets, and photographs for future reference
  • Brief client on findings — especially encroachments that may require action

Frequently Asked Questions

How long does a right-of-way survey take?

+

A residential ROW survey takes 2-4 weeks from authorization to delivery. FDOT corridor surveys for road widening projects take 4-8 weeks or longer depending on corridor length and the number of affected parcels. The breakdown: record research (3-10 days), field survey (1-5 days), office processing and ROW determination (1-2 weeks), and map preparation (1-2 weeks). Rush services may be available for residential projects.

How much does a right-of-way survey cost in Florida?

+

Residential ROW surveys cost $2,000-$5,000 depending on property size and record complexity. Commercial and corridor projects cost $5,000-$25,000+. FDOT corridor surveys are typically priced per linear foot ($5-$50/ft) depending on urban vs rural conditions, utility density, and required deliverables. Costs are driven primarily by the length of record research required — properties with complex deed histories or multiple ROW dedications cost more.

What is the difference between a ROW survey and a boundary survey?

+

A boundary survey maps the entire property boundary — all four (or more) sides. A ROW survey focuses specifically on the right-of-way boundary — typically the front of the property where it meets the road. A ROW survey also identifies encroachments into the ROW and locates improvements near the ROW line. Many projects combine both: a boundary survey that includes detailed ROW analysis. If you only need the ROW boundary and not the full property perimeter, a ROW-only survey is more focused and less expensive.

What is an encroachment into the right-of-way?

+

An encroachment is any physical object that extends into the legal right-of-way. Common encroachments include fences, retaining walls, landscaping, driveways (extending beyond the property line), mailbox posts, sprinkler systems, and building overhangs. Encroachments into public ROW are typically managed by the county or FDOT. Property owners may be required to remove encroachments, obtain a permit for them, or maintain them with an encroachment agreement.

Do I need a ROW survey before building a fence?

+

If your property borders a road, you should know where the ROW boundary is before installing a fence. A fence built inside the ROW may need to be removed at your expense. Many counties require a survey for fence permits near ROW. At minimum, have a surveyor locate the ROW line at your property frontage — this is less expensive than a full ROW survey and gives you the information you need to set your fence back from the ROW.

What is FDOT ROW acquisition?

+

When FDOT needs to widen a road or build new infrastructure, they may need to acquire additional right-of-way from adjacent property owners. This process involves: (1) a ROW survey to determine the existing and proposed ROW boundaries, (2) an appraisal of the land to be acquired, (3) negotiation with the property owner, and (4) if negotiation fails, eminent domain (condemnation) proceedings. Florida Statutes Ch. 337 and federal regulations govern this process.

Can I build within the right-of-way?

+

Generally no. The right-of-way is reserved for transportation and utility infrastructure. Permanent structures — buildings, fences, walls, swimming pools — are prohibited within the ROW. Some counties allow certain temporary or minor improvements (mailboxes, landscaping, driveways crossing the ROW) with an encroachment permit. FDOT has strict policies for their ROW. Check with your county public works department and verify the ROW boundary with a survey before making any improvements near the front of your property.

How do I find out where my right-of-way is?

+

Start with your county property appraiser GIS map — it typically shows the approximate ROW line. For precise location, hire a licensed Florida PSM to survey the ROW boundary. The surveyor researches recorded plats, road dedication documents, FDOT maps, and county records, then locates the ROW line in the field relative to your property corners. This is the only legally reliable method to determine the exact ROW boundary.

Need a Right-of-Way Survey?

Licensed Florida PSM team with ROW survey expertise — residential, commercial, and FDOT corridor projects. Serving all 67 counties.

Licensed PSM. Insured. Serving all 67 Florida counties.